Multimillion-Dollar Claim: Why Early Reporting Matters

When a Potential Problem Becomes a Multimillion-Dollar Claim: Why Early Reporting Matters

Two professional liability claim scenarios illustrate how seemingly routine project investigations can evolve into multimillion-dollar disputes—and why waiting for a formal demand or lawsuit to report a potential claim can be a costly mistake.

For architecture and engineering firms, professional liability claims rarely begin with a lawsuit arriving in the mail. More often, they start with something that appears relatively routine: an owner’s complaint, a request to investigate a building issue, a meeting about construction deficiencies or a discussion about potential repairs.

At the outset, these situations may seem manageable. The owner wants answers, the contractor is investigating, and the design professional believes the problem may ultimately be attributed to construction means and methods or another party’s work. There may be no formal accusation of negligence, no demand for money and no indication that litigation is imminent.

However, what begins as a cooperative effort to resolve a project issue can gradually develop into a substantial professional liability claim.

Two real-world-style claim scenarios illustrate how quickly these situations can escalate, the financial consequences of delayed reporting and the importance of involving a professional liability carrier early in the process.

Claim Scenario 1: The Parking Structure Investigation That Became a Multimillion-Dollar Claim

Six months after completing a multilevel parking structure, the owner reported extensive cracking in several elevated concrete slabs. The structural engineer was contacted and asked to participate in meetings with the owner, contractor and a forensic consultant retained to investigate the cause of the cracking.

Initially, the owner was careful not to accuse any project participant of wrongdoing. Rather, the owner explained that it simply wanted to understand what had happened and identify an appropriate repair strategy.

Because no formal demand had been made and no lawsuit had been filed, the engineer viewed the matter as a routine post-construction investigation. Believing the issue could be resolved through cooperation and technical analysis, the firm elected not to notify its professional liability carrier.

That decision would eventually prove costly.

From a Technical Investigation to a Dispute Over Responsibility

Over the next 18 months, the investigation expanded considerably. Core sampling, load testing and forensic analysis revealed widespread deficiencies that required extensive repairs and temporary shoring.

Parts of the parking facility were closed during the investigation, reducing available parking capacity and resulting in lost revenue for the owner.

As repair estimates increased, the nature of the discussions changed. What had initially been an effort to identify the cause of the cracking became a dispute over responsibility for the resulting damages.

The owner alleged that the structural design failed to adequately account for anticipated loading conditions and that design deficiencies contributed to the structural problems. Meanwhile, the contractor and subcontractors attempted to shift responsibility to the design team.

The engineer was no longer participating in a straightforward technical investigation. The firm was now facing allegations that its professional services had contributed to significant property damage and financial losses.

A Demand Exceeding $4.5 Million

The owner’s final demand exceeded $4.5 million and included:

  • Approximately $2.7 million in repair and remediation costs.

  • Nearly $1 million in business interruption and lost parking revenue.

  • Engineering and forensic consulting fees.

  • Attorneys’ fees and litigation expenses.

By the time the matter was reported, dozens of meetings had taken place, extensive written communications had been exchanged, and project participants had already established positions regarding the cause of the problem and responsibility for the damages.

Those early communications became an additional challenge for the defense.

Significant resources were required to reconstruct the chronology of events, review prior statements and address positions taken before coverage counsel and defense counsel became involved.

Following mediation, the matter was resolved for a confidential amount. Defense costs exceeded $450,000, and the insured ultimately contributed to a global settlement involving multiple defendants.

The Risk Management Lesson

The claim did not begin when the owner demanded $4.5 million. It began when the owner first asked the engineer to participate in investigating a potentially significant structural issue.

That initial request presented an opportunity to notify the professional liability carrier and obtain guidance before the investigation evolved into a formal dispute.

Early reporting could have allowed the carrier to assist with:

  • Developing an appropriate investigation and defense strategy.

  • Preserving relevant project documents, communications and other evidence.

  • Identifying and retaining qualified experts.

  • Coordinating communications with the owner, contractor and other project participants.

  • Evaluating potential exposure before positions became entrenched.

Instead, the engineer became involved in an increasingly contentious investigation without the benefit of early claims guidance.

The lesson is straightforward: An investigation does not have to involve an express allegation of negligence or a monetary demand to warrant consideration of notice under a professional liability policy.

Claim Scenario 2: A Water Infiltration Complaint Evolves Into $6 Million in Alleged Damages

An architectural firm received a letter from the owner of a recently completed mixed-use development alleging recurring water infiltration at multiple locations throughout the building envelope.

The owner requested project documents, invited the architect to participate in investigative meetings and explained that consultants were evaluating potential repair options.

The correspondence did not include a monetary demand or expressly accuse the architect of professional negligence.

The architect believed the contractor’s installation was the most likely source of the problem and anticipated that the issue could be resolved through the investigation and appropriate repairs. Consequently, the firm elected not to notify its broker or professional liability carrier.

At the time, the decision seemed reasonable. However, the problem would continue to grow over the next two years.

A Building Envelope Problem Becomes a Major Financial Exposure

As time passed, water intrusion continued to damage drywall, flooring, insulation and tenant improvements in several occupied spaces.

Multiple repair attempts failed to fully resolve the problem. Frustrated with the ongoing conditions, the owner retained a building envelope consultant and eventually authorized extensive destructive testing.

The investigation identified a combination of construction deficiencies and disputed design details involving flashing, waterproofing transitions and drainage components.

What initially appeared to be a localized repair issue had developed into a comprehensive building envelope problem.

Repair recommendations expanded accordingly, moving from isolated corrective work to an extensive remediation program.

As the scope and cost of repairs increased, questions about responsibility became more contentious. Although the architect continued to believe the contractor bore primary responsibility, the investigation increasingly focused on design decisions and coordination among the project participants.

Litigation and More Than $6 Million in Alleged Damages

The owner eventually filed suit against the architect, contractor, envelope consultant and numerous subcontractors.

The complaint sought more than $6 million in damages, including:

  • Approximately $3.8 million in repair and remediation costs.

  • More than $1.2 million in tenant relocation expenses and lost rental income.

  • Delay damages associated with remediation work.

  • Expert fees, attorneys’ fees and other litigation expenses.

By the time litigation commenced, the owner had accumulated years of correspondence, meeting minutes, consultant reports and repair records.

These documents became central to the dispute.

The architect’s position that the contractor was primarily responsible did not eliminate the firm’s exposure. Significant portions of the defense focused on design decisions, project communications and actions taken during the pre-suit investigation.

Although coverage ultimately applied, considerable time and expense were devoted to evaluating notice issues and reconstructing events that had occurred years before the matter was formally reported.

The case proceeded through extensive discovery before settling in mediation. Total defense costs exceeded $600,000, and the architect participated in a multiparty settlement that resolved the owner’s claims.

The Risk Management Lesson

Waiting for a lawsuit or formal monetary demand before considering professional liability notice can leave a firm unnecessarily exposed.

In this scenario, several developments could have signaled that a claim was emerging well before litigation began:

  • Written complaints alleging recurring building performance problems.

  • Requests for project documents and participation in formal investigations.

  • Retention of independent forensic or building envelope consultants.

  • Destructive testing and increasingly extensive repair recommendations.

  • Discussions about responsibility for design deficiencies and construction defects.

Any one of these developments may warrant consultation with the firm’s broker or carrier, depending on the circumstances and the policy’s reporting requirements.

Early reporting would have provided an opportunity to evaluate the situation, coordinate the investigation, preserve evidence and obtain claims guidance before the dispute escalated.

Even when a firm believes another project participant bears primary responsibility, that belief should not determine whether a potential claim is reported.

The Common Thread: Claims Often Develop Long Before Litigation

Although these two scenarios involve different disciplines and building systems, they share an important characteristic: Neither claim began with a lawsuit.

Both started with an owner reporting a project problem and asking the design professional to participate in an investigation.

In both situations, the design professional initially viewed the matter as a technical issue rather than a potential liability claim. Neither owner initially presented a substantial monetary demand or made an unequivocal allegation of negligence.

Yet, as investigations progressed and repair costs increased, the focus shifted from identifying the problem to assigning responsibility for the damages.

By the time formal claims emerged, significant time had passed, extensive communications had been exchanged and project participants had already taken positions that complicated the defense.

The financial consequences extended well beyond the cost of resolving the underlying allegations. Defense expenses alone exceeded $450,000 in the parking structure matter and $600,000 in the water infiltration matter.

These scenarios demonstrate why the timing of professional liability reporting can be just as important as the eventual merits of the claim.

Five Warning Signs That a Claim May Be Developing

Architecture and engineering firms should recognize that potential claims can emerge through routine project communications and investigative activities. The following warning signs deserve particular attention.

1. An owner reports a significant construction or building performance problem.

Cracking, water infiltration, structural movement, premature deterioration and other performance issues may initially appear to be warranty or construction matters. However, when the owner begins questioning whether professional services contributed to the problem, potential liability exposure may be developing.

2. The owner requests extensive project documentation.

Requests for drawings, calculations, specifications, meeting minutes, emails and other project records may be part of a legitimate investigation. However, they can also indicate that the owner or its consultants are evaluating potential claims against the design team.

3. Independent consultants or forensic experts are retained.

When an owner engages structural engineers, building envelope consultants, forensic specialists or other experts to investigate a project problem, the situation may be moving beyond routine troubleshooting.

4. Repair costs and alleged damages begin increasing.

A localized repair can become a comprehensive remediation project. Once temporary repairs fail, facilities are closed, tenants are displaced or business operations are disrupted, the financial exposure can increase significantly.

5. Project participants begin assigning responsibility.

Discussions about who designed, specified, installed, reviewed or approved particular components can signal a shift from problem-solving to potential dispute. When participants begin defending their respective roles, the firm should carefully evaluate its reporting obligations.

Why Early Reporting Makes a Difference

Professional liability insurance is not simply a resource to access after a lawsuit has been filed. Depending on the policy’s terms, reporting requirements and circumstances, early notice can provide an important opportunity for the carrier and its claims professionals to help manage a developing situation.

Early reporting may help firms:

  • Evaluate potential exposure: Claims professionals can help assess the circumstances and identify issues that may create professional liability exposure.

  • Preserve critical evidence: Early guidance can help ensure that project records, correspondence, calculations, photographs and other relevant materials are properly preserved.

  • Coordinate expert involvement: The carrier may assist with identifying appropriate experts and developing an effective investigative strategy.

  • Manage communications: Claims guidance can help firms avoid unnecessary statements, premature conclusions or communications that could complicate the defense.

  • Control defense costs: Addressing issues before positions harden and litigation begins may help reduce the time and expense associated with reconstructing events and responding to allegations.

Importantly, reporting a circumstance does not necessarily mean admitting fault or accepting responsibility. It allows the carrier to evaluate the situation and determine the appropriate next steps under the policy.

Firms should also understand that professional liability policies may contain specific provisions addressing claims, potential claims, circumstances, notice requirements and reporting deadlines. The applicable policy language matters, and firms should consult their broker or carrier rather than assume that notice can wait until a formal demand is received.

Conclusion: Don’t Wait for the Demand to Recognize the Claim

The parking structure and water infiltration scenarios illustrate a recurring challenge for architecture and engineering firms: The circumstances that eventually lead to a multimillion-dollar professional liability claim often develop gradually, beginning with what appears to be an ordinary project issue.

A cooperative investigation can become a dispute. A repair discussion can become a demand for damages. A technical disagreement can become litigation involving multiple defendants and hundreds of thousands of dollars in defense expenses.

By the time a formal demand arrives, valuable opportunities to manage the situation may already have been lost.

The most effective risk management approach is to recognize potential warning signs early, understand the reporting requirements of the firm’s professional liability policy and involve the broker or carrier when circumstances suggest that a claim may be developing.

The best time to report a potential claim is not necessarily when someone demands money or files a lawsuit. It is when the circumstances first indicate that the firm’s professional services may become the subject of a claim.

Early reporting is not an admission of liability. It is a proactive risk management decision that can help protect the firm, preserve its ability to defend itself and potentially reduce the financial consequences of an escalating dispute.

For additional information, please click HERE